Back | The first Combined Cycle Power Plant in Malaysia

Client
Asea Brown Boveri

Detail Narrative Description of Project

The project consisted of implementation of 4 Nos. Frame 13 Gas Turbine/Generator Sets.

Detail Description of Actual Services
Services provided included:

  • Detailed Engineering and Design of all civil and structural works.
  • Liaison with site for timely implementation of all civil works.
  • Gas Turbine/Generator Hall Foundation, Sub-Structure and Superstructure Steelworks.
  • Foundation for all equipments, etc.
  • External facilities e.g. roads, drains, cable/pipe trenches etc.

Project Completion
1992

copyright © Minconsult Sdn Bhd 2012-2020