Back | Khulna 150mw And Sirajganj 150mw Peaking Power Plants

Client
North-West Power Generation Co. Ltd.

Detail Narrative Description of Project
150MW Gas Turbine Generating Unit will be installed within proposed Sirajganj Combine Cycle Power Plant Project Area, which is close to the Jamuna Bridge. 150MW Khulna Peaking Power Plant will be installed within the existing Khulna Power Station area at Goalpara. (Including Power Evacuation to the Bangladesh National Grid)

Detail Description of Actual Services
Provide consulting services for Preliminary Design, Engineering, preparation of tender document, bid evaluation, approval of design, drawing, supervision of construction, installation, testing & commissioning, handing over plant including issuance of Provisional Acceptance Certificate (PAC) of the peaking power plants.