Back | Bang Bo Combined Cycle Power Plant Project, Thailand

Client
STP & I Public Company Limited, Thailand

Detail Narrative Description of Project
GT based combined cycle thermal power plant

Detail Description of Actual Services

  • Balance of Plant detailed piping engineering including stress analysis
  • BOP piping system include the following:
    - Fuel gas system
    - Distillate oil fuel system
    - Demineralised water system
    - Cooling water make-up system
    - Raw / Town water system
    - Main cooling water chemical dosing system
    - Cooling tower blowdown system
    - HRSG blowdown system
    - Compressed air system
    - Potable water system
    - Sanitary waste system (pressurized)
    - Operational waste water system (pressurized)