Back | Renovation, Installation and Commissioning of National Mail and Parcel Hub (NMPH)

Client
Pos Malaysia Berhad (PMB)

Detail Narrative Description of Project
This is the first automated mail processing centre in Malaysia using state of the art mail processing technologies capable of processing four million mail items per day.

Detail Description of Actual Services
Project Management Consultancy Service covering concept design, preparation of Tender Document, tender evaluation and award, contract administration, cost control, schedule control, quality assurance, construction management, health, safety and environment management, testing and commissioning.

Construction Cost
RM 160 Million

Project Completion
March 2011